XSD-TPMS-WI-BAT-WELD-20260804v1.12026-08-04Public TPMS Work InstructionEnglish

TPMS Battery Welding Work Instruction

This work instruction turns TPMS battery welding from operator-dependent practice into an authorized, verifiable and traceable process. The public version defines control logic; equipment programs and release limits must come from the actual material combination, process validation, customer requirements and project control plan.

Scope and document boundary

Applicable operations

Applies to approved tabbed cells, cell-to-tab joining, tab forming and related tab-to-PCB connection work.

Authorized personnel

Only personnel trained and authorized for safety, ESD, equipment, quality criteria and abnormal handling may perform the work.

Controlled inputs

The cell, tab, PCB, drawing, BOM, equipment program, fixture, electrodes, inspection specification and control plan must be current approved revisions.

Release principle

Appearance or pull strength alone does not prove system reliability; contact resistance, pulse sag, EOL and required reliability evidence are also needed.

Control boundary: This page is a public work-instruction framework for customer and quality review. It does not replace XSD Precision controlled shop-floor WIs, equipment parameter cards, product drawings, PFMEA, control plans, inspection specifications or customer-specific requirements. Welding current, energy, time, force, strength, resistance and sampling limits are product-specific validated values.

Pre-start condition checks

Check itemRequirementStop condition
Documents and work orderConfirm the work order, product, BOM, drawing, WI, control plan and equipment program revisions match; complete line clearance.Do not start when product or revision identity is inconsistent.
Cell and tabCheck supplier, model, lot, date, storage status, polarity, tab material, plating, thickness and surface cleanliness.Mixed lots, wrong polarity, oxidation, contamination, deformation or expired material are not permitted.
Equipment and fixtureConfirm calibration, locked program, fixture revision, force system, cooling, alarms and data acquisition are available.Stop for wrong program, expired calibration or unresolved alarms.
Electrodes and safetyCheck electrode material, face, wear, cleanliness and alignment; confirm short-circuit protection, eye protection, ESD and lithium-cell abnormal-response provisions.Do not use burned, offset, contaminated or end-of-life electrodes.

Standard operating steps

Clear the line and verify material

Count cells, tabs and PCBs against the work order, isolate unrelated material and record critical lot identities.

Call the controlled program

An authorized operator selects the locked program matched to the product, material stack and fixture. Similar-product parameters must not be substituted.

Load with polarity mistake-proofing

Locate the cell and tab against defined datums; verify polarity, stack direction, weld position, insulation clearance and anti-reversal controls.

Produce first-off welds

Make the specified first-off quantity and review equipment curves, alarms, expulsion, indentation, weld position and cell-seal condition.

Approve the first piece

Complete appearance, dimensions, joint strength and failure mode, four-wire resistance and required pulse-load checks.

Run controlled production

After approval, monitor program, force, electrodes, weld appearance, location and process signals at the control-plan frequency.

Form tabs and transfer

Use the specified direction and bend radius so the weld nugget and cell seal do not become secondary bend points; maintain short-circuit clearance.

Complete EOL and lot release

Link polarity, static voltage, sleep current, wake-up, pulse sag, RF/EOL and audit records to the serial number or batch.

Critical process control table

Control itemCritical inputOperating requirementRetained evidence
Program and energyEquipment program, waveform, current or energy, pulse time and monitoring limitsUse only the validated approved program; any adjustment requires authorization and renewed first-piece approval.Process curves, alarms and first-piece record
Electrode systemMaterial, face, force, alignment, cleanliness, wear and replacement lifeClean and confirm at the defined frequency; replace for end of life, offset wear or burning.Electrode maintenance record
Stack and locationPolarity, tab direction, overlap, weld location and distance from the cell sealUse mechanical or vision mistake-proofing rather than operator memory.First-piece image or dimensional record
Appearance and heat effectExpulsion, burn-through, cracks, abnormal indentation, plating damage, insulation damage and seal deformationStop and isolate immediately; cosmetic rework cannot replace root-cause confirmation.100% appearance confirmation and nonconformance record
Joint performancePull or shear result, failure location, four-wire contact resistance and pulse voltage sagEvaluate both value and failure mode; static low resistance does not replace real transmit-load testing.Sampling, destructive audit and trend
Tab formingBend location, direction, radius, preload and stress at the PCB connectionDo not create a secondary bend at the nugget, cell seal or PCB joint.Forming first-piece and patrol record

First-piece, patrol and periodic audits

Inspection levelCheck contentTrigger or frequencyRelease rule
100% operation checkMaterial identity, polarity, program, location, weld appearance, insulation clearance and equipment result.Every part / automatic or manual mistake-proofingNonconforming parts cannot transfer.
First-piece inspectionAppearance, dimensions, pull or shear, failure mode, four-wire resistance and project-defined dynamic checks.Start of shift, lot or model change, program or electrode change, repair or restartProduction begins only after authorized approval.
Process patrolEquipment curves, force, electrodes, weld location, expulsion, tab forming and process trend.Control-plan frequencyTrace back to the last accepted point after an excursion.
Periodic destructive auditNugget, section, strength, failure mode and electrode-life boundary.Based on product risk, volume and control planConfirms the process window remains effective.
EOL system validationPolarity, static voltage, sleep current, wake-up, pressure and temperature reading, RF transmission and traceability binding.Product EOL specificationSystem failures cannot be packed or released.
Reliability auditCold pulse load, thermal cycling, vibration, mechanical shock, centrifugal load and pre/post-aging comparison.Validation plan and change riskConfirms long-term margin in the target environment.

Abnormal handling and rework limits

Abnormal conditionImmediate actionRestart boundary
Equipment alarm, signal excursion or wrong programStop, lock the program, isolate work since the last accepted check and notify engineering and quality.Do not restart before cause confirmation and a new first piece.
Expulsion, burn-through, abnormal indentation or seal deformationStop and inspect electrodes, force, location, contamination and program selection; retain failed samples.Grinding or rewelding does not authorize release.
Strength, failure-mode or resistance failureIsolate the lot and related time window, verify fixture and test method, then perform tightened validation and impact review.Do not respond only by increasing welding energy.
Wrong polarity, short circuit or insulation damageControl the safety risk, isolate under the lithium-cell response procedure and trace the mistake-proofing failure across the lot.Affected cells must not be reused.
Rework requestUse only an approved rework specification that evaluates added heat input, weld location and cell-seal risk; record count and approval.Without a validated rework route, treat the part as nonconforming.

Release records and change control

Record categoryMinimum retained content
Lot traceabilityWork order, product, serial or lot, cell, tab, PCB, housing and potting-material lots.
Equipment traceabilityMachine, program revision, fixture, electrode, calibration, maintenance, cleaning, replacement and process curves.
Personnel traceabilityOperator, first-piece approver, patrol inspector, abnormal reviewer and release authority status.
Quality evidenceAppearance, dimensions, strength, failure mode, contact resistance, pulse sag, EOL and reliability results.
Change controlCell, tab, plating, equipment, program, electrode, fixture, PCB, solder, housing, potting and EOL-software changes.

Frequently asked questions and references

Frequently asked questions

Can a standard coin cell be soldered directly with an iron?

Do not apply a soldering iron directly to a standard cell case unless the cell supplier has explicitly approved the cell structure and process. Use supplier-approved tabbed cells or a validated joining route.

Why does the public instruction not give one fixed welding parameter?

Cell case, tab material and thickness, electrodes, equipment, fixture and product structure all change the process window. Copying another product’s values can cause weak joints, burn-through or seal damage.

Is a passing pull result enough for release?

No. Failure mode, contact resistance, real pulse load, EOL and required environmental and mechanical evidence must also be considered.

Can an unacceptable weld be rewelded?

Only under a validated approved rework specification. A second weld adds heat and mechanical risk and is not a default recovery method.

Reference basis

To convert this public framework into a product-specific controlled WI, parameter validation, PFMEA, control plan or abnormal analysis, submit the cell, tab, equipment, fixture, PCB, package and validation requirements.

Submit TPMS battery welding review inputs
XSD Precision

Resource Scope and Project Inputs

This module helps readers convert website guidance into reviewable RFQ and project inputs for XSD Precision engineering communication.

Who This Resource Is For

TPMS sourcing, service, channel and engineering teams confirming OE numbers, vehicle year and market, frequency, programmable-sensor coverage and vehicle relearn validation boundaries.

Project Inputs

OE number, vehicle year, target market, 315MHz / 433MHz frequency, programming tool, sensor sample, activation/read results and relearn conditions.

How XSD Precision Uses This Information

The website explains decision logic, input checklists, validation paths and collaboration methods. Vehicle programs, test records, software details, quality records and project confirmation materials are reviewed through direct project communication.

Next steps

Turn the reading result into reviewable project inputs

If this article narrows the direction, the next step is not a generic inquiry: prepare vehicle, drawing, material, volume, quality or testing boundaries so XSD Precision can review the project route.

Product catalog and capability evidence links

Related resources

XSD-TPMS-MS-5318 TPMS Traceability for Distributors, Service Networks, and OEM/ODM Programs Market Strategy / TPMS XSD-TPMS-MS-4684 Keeps TPMS Sensor After-Sales Service Controllable Market Strategy / TPMS XSD-TPMS-EG-4663 Manufactures High-Quality TPMS Sensors Engineering Guide / TPMS

Prepare these inputs before sending

  • Vehicle, year, target market or OE number
  • Frequency, valve, material, drawings or sample photos
  • Estimated quantity, packaging, test conditions and timing